Dongkuk Steel – Incheon DC EAF (Newly Installed)
- Scale : 100Ton DC Electric Arc Furnace, Heating Furnace
- Main Products : Reinforcing Bars, etc.
- Annual Production Capacity : 900k Ton
- In Operation Since : 1992
Our Participation in the Project
- - Designing of Refractories Installation Profile
- - Supply and Installation of Refractories
- - Transfer speed: 29.2mm/min(Max), 360mm/12.3min
- - Total Operations Management of Refractories Installation Contractors
Dongkuk Steel – Incheon ECO ARC (Newly Installed)
- Scale : 120Ton AC EAF, Heating Furnace
- Main Products : Reinforcing Bars, etc.
- Annual Production Capacity : 1mil Ton
- In Operation Since : October 2010
Our Participation in the Project
- - Designing of Refractories Installation Profile (EAF Profile designed by Shinagawa)
- - Supply and Installation of Refractories (Some refractories are supplied by imports)
- - Total Operations Management of Refractories Installation Contractors Total Operations Management of Refractories Installation Contractors
Dongkuk Steel – Pohang DC EAF (Newly Installed)
- Scale : 140Ton DC TWIN EAF, Heating Furnace
- Main Products : Reinforcing Bars, Sections, etc.
- Annual Production Capacity : 1.4mil Ton
- In Operation Since : 1996
Our Participation in the Project
- - Designing of Refractories Installation Profile
- - Supply and Installation of Refractories
- - Total Operations Management of Refractories Installation Contractors
KISCO – Changwon DC EAF (Newly Installed)
- Scale : 120Ton DC EAF, Heating Furnace
- Main Products : Reinforcing Bars, etc.
- Annual Production Capacity : 1mil Ton
- In Operation Since : 1992
Our Participation in the Project
- - Designing of Refractories Installation Profile
- - Supply and Installation of Refractories
- - Total Operations Management of Refractories Installation Contractors
KISCO – Chang Won AC EAF (Newly Installed)
- Scale : 70Ton AC EAF, Heating Furnace
- Main Products : Blister Steels, Sections, etc.
- Annual Production Capacity : 300k Ton
- In Operation Since : 2007
Our Participation in the Project
- - Designing of Refractories Installation Profile
- - Supply and Installation of Refractories
- -Total Operations Management of Refractories Installation Contractors
KOSCO - AC EAF (Newly Installed)
- Scale : 100Ton AC EAF
- Main Products : Special Steels, General Billets, etc.
- Annual Production Capacity : 800k Ton
- In Operation Since : 2008
Our Participation in the Project
- - Designing of Refractories Installation Profile
- - Supply and Installation of Refractories
- - Total Operations Management of Refractories Installation Contractors
PT.HANIL JAYA STEEL - AC EAF (NewLy Installed)
- Scale : 50Ton AC EAF (Newly Installed)
- Main Products : Special Steels, General Billets, etc.
- Annual Production Capacity : 300k Ton
- In Operation Since : 2010
Our Participation in the Project
- - Designing of Refractories Installation Profile
- - Supply of Refractories
- - Technical Support for Refractories Installation
Summary
Group
|
Factory
|
Equipment
|
No of Units
|
Main Products
|
Annual Capacity (thousands)
|
Dongkuk Steel Group
|
Incheon Works
|
100TON DC EAF |
1 |
Reinforcing Bars, etc
|
90ton
|
120TON ECO-ARC |
1 |
Reinforcing Bars, etc
|
100ton
|
Pohang Works
|
140TON DC EAF (TWIN TYPE) |
1 |
Sections, Reinforcing Bars, etc
|
140ton
|
KISCO Group
|
KISCO Changwon Factory
|
100TON DC EAF |
1 |
Reinforcing Bars, etc |
100ton
|
70TON AC EAF |
1 |
Blister Steels, Reinforcing Bars, etc
|
80ton
|
KOSCO
|
100TON AC EAF |
1 |
Special Steels, etc.
|
80ton
|
HANSCO
|
100TON DC EAF
|
1 |
Reinforcing Bars, etc |
80ton
|